What to Send for a Panel Quote
The eight things that get you an accurate quote the first time.
A custom industrial control panel from WETS AI takes about 16 weeks on average from order to shipment. The time is spent on engineering and drawing approval, buying components, building and wiring, and testing. Component purchasing usually takes the longest, because drives, PLCs and enclosures can have long lead times. Each quotation comes with its own schedule.
An example of how a typical project is scheduled. Some steps overlap, which is how the total is kept down.

Most panel parts come from distributor stock, but some do not. Larger drives, PLC families in high demand, stainless enclosures and enclosure air conditioners can take many weeks to arrive.
A panel cannot ship until its last part arrives, so the slowest component often sets the delivery date. We check lead times while quoting and tell you which parts drive the schedule.
Most delays come from waiting: for information, for approvals or for parts. These steps cut the waiting.
| Do this | Effect |
|---|---|
| Send complete information with the request | The quote and drawings start without a round of questions. |
| Approve drawings quickly | Purchasing cannot start until the design is fixed. |
| Release long-lead parts early | Drives and PLCs can be ordered while details are still being agreed. |
| Accept equal alternatives | An in-stock equivalent can save weeks over a backordered part. |
| Book the FAT date early | Testing slots are planned into the build schedule. |
When drawings and parts lists are already released, engineering time drops away and parts can be ordered on day one. OEMs who order the same panel regularly can also agree stock levels for long-lead parts.
Prototype panels go the other way: the first unit takes longer because the design is still being proven, and the lessons go back into the drawings for the units that follow.

About 16 weeks on average from order to shipment. The real figure depends on panel size and on component lead times, so we confirm a schedule with every quotation.
Often, yes, when the design is simple, drawings are ready and the parts are in stock. Tell us your date and we will say honestly whether it can be met.
Usually not much. Programming runs alongside the build, so the program is ready for testing when the panel is.
From order and the information needed to start. Drawing approval and long-lead part release are the two dates that matter most.
The eight things that get you an accurate quote the first time.
The choices that move the price of a panel up or down.
The same panel, built the same way, for every machine you ship.
Send what you have: drawings, an I/O list or a short description of the process. We will reply with questions, a quotation and a schedule.