Guide

Control Panel Lead Times: Where the Weeks Go

A custom industrial control panel from WETS AI takes about 16 weeks on average from order to shipment. The time is spent on engineering and drawing approval, buying components, building and wiring, and testing. Component purchasing usually takes the longest, because drives, PLCs and enclosures can have long lead times. Each quotation comes with its own schedule.

Example Schedule

What Happens in Those 16 Weeks

An example of how a typical project is scheduled. Some steps overlap, which is how the total is kept down.

  • Long-lead parts are released as drawings are approved
  • Other parts follow once the design is fixed
  • Building starts when the main parts arrive
  • Testing and FAT happen before shipping
Example Gantt chart of a 16-week control panel schedule: engineering and drawings in weeks 1 to 4, drawing approval in weeks 4 to 5, component purchasing from week 4 to week 12, build and wiring in weeks 10 to 14, testing and FAT in weeks 14 to 15, and shipping in week 16.
Swipe sideways to see the whole diagram
Variable frequency drives mounted for motor speed control
Variable frequency drives, often a long-lead item
What Sets the Pace

Why Purchasing Usually Takes Longest

Most panel parts come from distributor stock, but some do not. Larger drives, PLC families in high demand, stainless enclosures and enclosure air conditioners can take many weeks to arrive.

A panel cannot ship until its last part arrives, so the slowest component often sets the delivery date. We check lead times while quoting and tell you which parts drive the schedule.

Saving Time

How to Shorten the Schedule

Most delays come from waiting: for information, for approvals or for parts. These steps cut the waiting.

Do thisEffect
Send complete information with the requestThe quote and drawings start without a round of questions.
Approve drawings quicklyPurchasing cannot start until the design is fixed.
Release long-lead parts earlyDrives and PLCs can be ordered while details are still being agreed.
Accept equal alternativesAn in-stock equivalent can save weeks over a backordered part.
Book the FAT date earlyTesting slots are planned into the build schedule.
Repeat Panels

Repeat Orders Are Faster

When drawings and parts lists are already released, engineering time drops away and parts can be ordered on day one. OEMs who order the same panel regularly can also agree stock levels for long-lead parts.

Prototype panels go the other way: the first unit takes longer because the design is still being proven, and the lessons go back into the drawings for the units that follow.

PLC control panel interior with I/O modules, relays, starters and wire duct
PLC panel interior ready for a repeat build
FAQ

Common Questions

How long does a panel take?

About 16 weeks on average from order to shipment. The real figure depends on panel size and on component lead times, so we confirm a schedule with every quotation.

Can you build a panel faster than 16 weeks?

Often, yes, when the design is simple, drawings are ready and the parts are in stock. Tell us your date and we will say honestly whether it can be met.

Does programming add to the lead time?

Usually not much. Programming runs alongside the build, so the program is ready for testing when the panel is.

When does the schedule start?

From order and the information needed to start. Drawing approval and long-lead part release are the two dates that matter most.

Related

Related Guides & Services

Panels for OEMs

The same panel, built the same way, for every machine you ship.